Location Cape Lambert

Services Relocation & Demobilisation

Duration 5 days

Client GCS Hire

Grounded Construction Group were engaged to complete the demobilisation of a 12 x 21m (7 floors) temporary office building from the Rio Tinto Cape Lambert site on behalf of GCS Hire.

We were required to decomplex the building and decommission all electrical and plumbing connections prior to separating each floor. Each floor was transit sheeted ready for transport and craned onto trucks along with the concrete blocks used under each building.