Stork Road, South Hedland

Friday, June 13, 2014

 

South Hedland is a suburb in the town of Port Hedland, in the Pilbara region, North-Western WA

Grounded Construction Group were engaged by Aussie Modular Solutions to complete the installation of this modular house. Works completed included:

  • Earthworks & footings
  • Installation of 3 Bedroom & 2 Bathroom Modular House
  • Inground services Plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

This house was installed at the same time as the Raven Street house. Grounded completed the works to both sites concurrently so allow handover of both houses at the same time.

Rio Tinto Wickham Development

Friday, June 13, 2014

 

Grounded Construction were contracted by Aussie Modular Solutions to complete the installation of 30 modular houses for the Rio Tinto Wickham Housing Project.

The 30 houses consisted of two configurations and they were:

  • 18 x 3 bedrooms and 2 bathrooms
  • 12 x 4 bedrooms and 2 bathrooms

The scope of work included:

  • Placement and landing of each house
  • Internal and external complexing of the buildings
  • Plumbing and electrical interfloor connections
  • Transit repairs to buildings

 

 

 

Raven Street, South Hedland

Friday, June 13, 2014

 

South Hedland is a suburb in the town of Port Hedland, in the Pilbara region, North-Western WA

Grounded Construction Group were engaged by Aussie Modular Solutions to complete the installation of this modular house. Works completed included:

  • Earthworks & footings
  • Installation of 3 Bedroom & 2 Bathroom Modular House
  • Inground services Plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

This house was installed at the same time as the Stork Road house. Grounded completed the works to both sites concurrently so allow handover of both houses at the same time.

 

Lot 666 Anketell Court, Onslow

Friday, June 13, 2014

 

Grounded Construction were engaged to complete the full installation of this three unit site in Onslow, providing a turnkey service for our client.

Each unit comprised of 3 x bedroom and 2 x bathroom over a two floor designed modular house. The works involved were:

  • Site Works including earthworks & footings
  • Supply and installation of precast concrete style retaining walls
  • Landing and placement of the modular houses
  • Internal and external complexing of each modular house
  • Installation and connection of in ground plumbing and electrical services to suit strata requirements
  • Installation of exposed aggregate concrete paths & driveways
  • Install carports, porches & alfresco’s
  • Install fencing and gates
  • Internal and external painting
  • Landscaping to each house and common areas

 

Homestead Ramble, Newman

Saturday, June 7, 2014

 

Newman is a town in the Pilbara region of WA It is located about 1,186 kilometres north of Perth

Grounded Construction were engaged by Aussie Modular Solutions to install a 4×2 modular house. The scope of works included:

  • Earthworks & footings
  • Landing and placement of the modular house (consisting of 3 floors)
  • Internal and external complexing
  • Inground services for plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

 

Contact


Grounded Construction Group Pty Ltd

08 9321 3398
Suite 7, Level 3
1111 Hay Street
West Perth, WA 6005

ABN 69 166 112 429

Mid-West Depot


418 Robinson Street, Carnarvon, WA 6701