Port Hedland Power Station

Tuesday, July 1, 2014

 

Grounded Construction Group were engaged to decommission onsite temporary buildings at the Port Hedland Power Station.

The project included decommissioning all electrical and plumbing services to the buildings and preparing them for transport. Grounded Construction organised cranage onto trucks and transport to their new location.

Rio Tinto Cape Lambert

Tuesday, July 1, 2014

 

Grounded Construction Group were engaged to complete the demobilisation of a 12 x 21m (7 floors) temporary office building from the Rio Tinto Cape Lambert site on behalf of GCS Hire.

We were required to decomplex the building and decommission all electrical and plumbing connections prior to separating each floor. Each floor was transit sheeted ready for transport and craned onto trucks along with the concrete blocks used under each building.

FMG Dally Camp 900 Person

Wednesday, June 25, 2014

 

60km North of Tom Price, Pilbara, WA is where you will find the FMG Solomon site.

Grounded Construction Group were engaged by McNally Group to complete the refurbishment of several of the Dally camps buildings. These works included:

  • Re complex Kitchen
  • Re complex Wet Mess
  • Re complex accommodation units
  • Re complex central facilitates
  • Installation of verandahs

Stork Road, South Hedland

Friday, June 13, 2014

 

South Hedland is a suburb in the town of Port Hedland, in the Pilbara region, North-Western WA

Grounded Construction Group were engaged by Aussie Modular Solutions to complete the installation of this modular house. Works completed included:

  • Earthworks & footings
  • Installation of 3 Bedroom & 2 Bathroom Modular House
  • Inground services Plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

This house was installed at the same time as the Raven Street house. Grounded completed the works to both sites concurrently so allow handover of both houses at the same time.

Rio Tinto Wickham Development

Friday, June 13, 2014

 

Grounded Construction were contracted by Aussie Modular Solutions to complete the installation of 30 modular houses for the Rio Tinto Wickham Housing Project.

The 30 houses consisted of two configurations and they were:

  • 18 x 3 bedrooms and 2 bathrooms
  • 12 x 4 bedrooms and 2 bathrooms

The scope of work included:

  • Placement and landing of each house
  • Internal and external complexing of the buildings
  • Plumbing and electrical interfloor connections
  • Transit repairs to buildings

 

 

 

Raven Street, South Hedland

Friday, June 13, 2014

 

South Hedland is a suburb in the town of Port Hedland, in the Pilbara region, North-Western WA

Grounded Construction Group were engaged by Aussie Modular Solutions to complete the installation of this modular house. Works completed included:

  • Earthworks & footings
  • Installation of 3 Bedroom & 2 Bathroom Modular House
  • Inground services Plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

This house was installed at the same time as the Stork Road house. Grounded completed the works to both sites concurrently so allow handover of both houses at the same time.

 

Rio Tinto HD4

Friday, June 13, 2014

 

Temporary buildings relocation. The Hope Downs mine is an iron ore mine located in the Pilbara region of WA 100 kilometres northwest of Newman.

  • GCS temporary office buildings

Roy Hill Samsung & Boodarie Sites

Friday, June 13, 2014

 

Grounded Construction Group were engaged by GCS Hire to land temporary buildings at the Roy Hill Samsung and  Boodarie sites just out of South Hedland.

Our scope of work included the craning and placement of the buildings, followed by the building complexing and installation of electrical and mechanical services.

For this project we installed:

  • Office Building
  • Crib Room
  • 6 Pan Ablution Block
  • 80kVa generator

 

Lot 666 Anketell Court, Onslow

Friday, June 13, 2014

 

Grounded Construction were engaged to complete the full installation of this three unit site in Onslow, providing a turnkey service for our client.

Each unit comprised of 3 x bedroom and 2 x bathroom over a two floor designed modular house. The works involved were:

  • Site Works including earthworks & footings
  • Supply and installation of precast concrete style retaining walls
  • Landing and placement of the modular houses
  • Internal and external complexing of each modular house
  • Installation and connection of in ground plumbing and electrical services to suit strata requirements
  • Installation of exposed aggregate concrete paths & driveways
  • Install carports, porches & alfresco’s
  • Install fencing and gates
  • Internal and external painting
  • Landscaping to each house and common areas

 

Homestead Ramble, Newman

Saturday, June 7, 2014

 

Newman is a town in the Pilbara region of WA It is located about 1,186 kilometres north of Perth

Grounded Construction were engaged by Aussie Modular Solutions to install a 4×2 modular house. The scope of works included:

  • Earthworks & footings
  • Landing and placement of the modular house (consisting of 3 floors)
  • Internal and external complexing
  • Inground services for plumbing & electrical
  • Concrete paths & driveways
  • Installation of carport, porch & alfresco
  • Fencing

 

Contact


Grounded Construction Group Pty Ltd

08 9321 3398
Suite 7, Level 3
1111 Hay Street
West Perth, WA 6005

ABN 69 166 112 429

Mid-West Depot


418 Robinson Street, Carnarvon, WA 6701